MIDC supplies water to units in its industrial areas. A new factory applies for a connection based on its estimated daily requirement.
Before applying
- Prepare a water balance: process, cooling, domestic and gardening use
- Check that the same figures match your MPCB application
- Plan storage tanks for at least a day of consumption
Typical steps
- Application to MIDC with plot and requirement details
- Payment of deposit and connection charges
- Meter installation and connection
- Monthly billing as per MIDC tariffs
Until the connection is ready
During construction and early trials, many units rely on water tankers.
We include the water connection in our MIDC approvals package.